Write a concrete event

Replace vague labels with a possible cause and project effect. “Difficult integration” is less actionable than “test access arrives after field validation is due.” Separate future risks from existing problems and record available evidence.

Assign signals and responses

Assign an owner, trigger and possible response. Use simple priority scales without inventing statistical probabilities. Add a review date. Mitigation should change exposure or consequences; “monitor closely” needs a specific check and intervention point.

Test a trigger

Example: if the catalogue is unapproved at content freeze, publish confirmed services and reschedule the remainder. Walk through this with scope and schedule owners. Each major risk needs an executable step and clarity about commitments requiring renegotiation.

Key takeaways

  • Describe events, signals and responses someone can recognise and execute.